Sheffield Children's Hospital
One of only four specialist children’s hospital trusts in the country, the new look Sheffield Children’s Hospital outpatient’s department opened in November 2016. The project included building a brand-new reception area with ribba wall cladding, consultation rooms, bedrooms. The work allowed for not only a better overall patient experience but provided improved healthcare facilities.
Main Contractor:
Simons Construction
Client:
Sheffield Children's Hospital Trust
Sector:
Healthcare
Package Value:
£2.4m
Services provided
Structural Fire Protection Demountable Glazed Screens Joinery SFS Refurbishment & MaintenanceSectors
HealthThe second phase of this project completed in 2017- a two-storey refurbishment within the existing building provided further patient bedrooms.
Horbury Joinery Ltd undertook the following works:
- Installation of a new reception area, patient bedrooms and consultation rooms
- Refurbishment within existing building to provide further patient bedrooms
- Design and installation of bespoke ribba wall panelling
- Door and ironmongery design and installation
- Installation of glazed screens.
Titan Interior Solutions Ltd undertook the following works:
- Installation of British gypsum partitions, shaft walls and linings
- Installation MF ceilings, perimeter margins and rockfon lay-in grid ceiling tiles
- High level feature atrium rooflights
- SFS atrium walls to support ribba panelling
- Basement soffit insulation
- Fire rated beam encasements to existing beams in the refurbishment
- Soft flooring installation.